However, CRS reports, “The Navy’s FY2013 30-year (FY2013-FY2042) shipbuilding plan, which was submitted to Congress on March 28, 2012 (more than a month after the submission of the FY2013 budget on February 13, 2012), does not include enough ships to fully support all elements of the Navy’s 310-316 ship goal over the long run.
The Navy projects that the fleet would remain below 310 ships during the entire 30-year period, and experience shortfalls at various points in ballistic missile submarines, cruisers-destroyers, attack submarines, and amphibious ships.”
The projected cruiser-destroyer and attack submarine shortfalls are smaller than they were projected to be under the FY2012 30-year (FY2012-FY2041) shipbuilding plan, CRS says, due in part to a reduction in the cruiser-destroyer force-level goal and the insertion of additional destroyers and attack submarines into the FY2013 30-year plan.